问题: 违约赔偿金的翻译

In case of any failure whatsoever towards meeting the agreed Delivery Schedule a mentioned in Schedule 4, the Supplier shall be liable to pay to the Purchaser Liquidated Damages, and not by way of penalty, an amount calculated at the rate of 0.5% (half percent) of the delayed month wise shipment for each week of delay or part thereof subject to a maximum of 10% of Contract Price.

解答:

如卖方未能履行计划4中所提及的交货计划,卖方应向买方支付违约损失赔偿金,该项赔偿金不应视为罚款;迟交货以月为计算单位,每迟交
一星期或不足一星期赔偿额按合同价格的0.5%计算,最高赔偿额为合同
价格的10%。